The project involved more than 5 months of comprehensive logistics planning and engineering studies. This transport included four power transformers, each with a unit weight of 354 Mtons, and four shunt reactors with a unit weight of 135 Mtons each. The total project consisted of over +3250 Frt.


Logistics Challenge
The initial challenge was related to the storage area constraint at the manufacturer’s factory. To overcome this issue, COLI’s Istanbul team provided a designated warehouse solution with suitable ground bearing capacity and route feasibility in order to ensure safe intermediate deliveries from the factory. The second challenge was getting the cargoes from the warehouse to the port of loading, which required precise coordination with road authorities and loadport management.


Permits and Protocols
During the entire planning period, all necessary permit applications and road protocols were obtained and a thorough logistics plan was shared to successfully keep all involved parties on the same wavelength. Arranging the permit applications for this exceptional load transport was a complex project in itself – on top of the engineering studies, calculations and, of course, the transportations themselves.


Equipment
With, amongst others, 140 hydraulic axle lines, a girder bridge configuration, 20 SPMT axle lines, a 1,000 Mton capacity gantry crane, and +70 trailers being utilized throughout the project period, it was satisfying to see that all requirements were met (and all obstacles were overcome) to satisfaction, not in the least because of the professional collaboration between Coli’s team, the subcontractors and other stakeholders. After safely arriving to port of loading and handling continuous vessel loading operations for four days , all cargoes were smoothly delivered to Gydnia, Poland.

COLI Logistics is a member of Cross Ocean representing Germany, Turkey & Guyana

View Profile:  COLI Logistics GmbH | Coli Project Cargo Istanbul | COLI Shipping & Transport (Guyana) Inc.